Carolina Builders Corp. v. Cenit Equity Co.

Present:   All the Justices

CAROLINA BUILDERS CORPORATION

v. Record No. 980519   OPINION BY JUSTICE CYNTHIA D. KINSER
                                      February 26, 1999
CENIT EQUITY COMPANY

             FROM THE CIRCUIT COURT OF YORK COUNTY
                    Thomas B. Hoover, Judge


     In this appeal, we decide two issues: (1) the date

from which the 150-day limitation period in Code § 43-4 is

calculated for purposes of determining what sums can be

included in a memorandum of mechanic’s lien; and (2)

whether including only sums due for labor performed or

materials furnished during the 150-day limitation period is

a prerequisite for perfecting a mechanic’s lien, thereby

invalidating a lien that includes sums due for labor

performed or materials furnished prior to the 150-day

period.    Because we conclude that the 150-day limitation

period is computed from the last day that labor is

performed or material is furnished to a job preceding the

filing of a memorandum of mechanic’s lien and that

including only labor and materials furnished during the

150-day limitation period is a prerequisite for perfecting

the lien, we will affirm the judgment of the circuit court

invalidating a mechanic’s lien.

                                I.
     Carolina Builders Corporation (Carolina Builders)

filed a memorandum of mechanic’s lien on July 29, 1996,

against a certain tract of real estate located in York

County for sums owed to Carolina Builders for materials

that it had furnished for construction of a residential

dwelling on the property.    Subsequently, on January 27,

1997, Carolina Builders filed a bill to enforce the

mechanic’s lien and named Cenit Equity Company (Cenit) as

one of the defendants.

     After conducting discovery, Cenit filed a petition to

declare the mechanic’s lien invalid pursuant to Code § 43-

17.1 1 and a motion for summary judgment.   Cenit asserted

that the mechanic’s lien sought to be enforced by Carolina

Builders was invalid under Code § 43-4 because it included

sums due for materials furnished more than 150 days prior

to the last date on which labor was performed or material

was furnished to the job preceding the filing of the

memorandum.


     1
         Code § 43-17.1 provides, in pertinent part:

          Any party, having an interest in real property
     against which a lien has been filed, may . . .
     petition the court of equity having jurisdiction . . .
     to hold a hearing to determine the validity of any
     perfected lien on the property. . . . If the court
     finds that the lien is invalid, it shall forthwith
     order that the memorandum or notice of lien be removed
     from record.

                               2
     At a hearing on November 6, 1997, the parties

stipulated the following facts:

     1. Carolina Builders filed the memorandum of
     mechanic’s lien on July 29, 1996.

     2. The memorandum of mechanic’s lien included sums
     due for materials furnished by Carolina Builders from
     December 6, 1995, through April 16, 1996.

     3. May 23, 1996, was the last day that Carolina
     Builders furnished materials to the job prior to
     filing the memorandum of mechanic’s lien.

     4. Counting back from May 23, 1996, the 150-day
     period ended on December 25, 1995.

     5. The memorandum of mechanic’s lien included amounts
     owed for materials furnished prior to December 25,
     1995, specifically from December 6 through 15, 1995.

     After considering memoranda and argument by the

parties, the circuit court determined that the 150-day

period must be calculated back from May 23, 1996, the last

day that Carolina Builders furnished materials to the job

immediately preceding the date that it filed the

memorandum.   Thus, the court concluded that the mechanic’s

lien violated Code § 43-4 because it included amounts owed

to Carolina Builders for materials provided to the job

prior to the 150-day period.    In a final decree dated

December 18, 1997, the court held that the mechanic’s lien

was invalid and unenforceable, and granted summary judgment

in favor of Cenit.   Carolina Builders appeals.

                               II.


                                3
     Code § 43-4 contains two distinct time limitations.

The first one requires that a memorandum of mechanic’s lien

be filed “not later than ninety days from the last day of

the month in which [the lien claimant] last performs labor

or furnishes material, and in no event later than ninety

days from the time such building, structure, or railroad is

completed, or the work thereon otherwise terminated.”      Code

§ 43-4.   No one disputes that Carolina Builders complied

with this 90-day rule.   It is the second limitation that is

at issue in this appeal.   That provision specifies that

“[t]he lien claimant may file any number of memoranda but

no memorandum . . . shall include sums due for labor or

materials furnished more than 150 days prior to the last

day on which labor was performed or material furnished to

the job preceding the filing of such memorandum.”      Code

§ 43-4.

     Carolina Builders’ memorandum of mechanic’s lien

included sums due for materials furnished from December 6,

1995, through April 16, 1996.       Therefore, it argues that

the 150 days should be counted back from April 16 rather

than from May 23, 1996, even though the latter date was

when Carolina Builders last delivered materials before

filing the memorandum.   In other words, Carolina Builders

asserts that the last date actually included in the


                                4
mechanic’s lien for materials furnished to the job should

be the operative date from which to calculate the 150-day

limitation period set out in Code § 43-4.   We do not agree.

     We have previously stated that Code § 43-4 is “clear

and unambiguous.”    Dominion Trust Co. v. Kenbridge Constr.

Co., Inc., 248 Va. 393, 396, 448 S.E.2d 659, 660 (1994).

If the statute as written is clear on its face, this Court

will look no further than the plain meaning of the

statute’s words.    City of Winchester v. American Woodmark

Corp., 250 Va. 451, 457, 464 S.E.2d 148, 152 (1995).     In

applying the plain meaning rule, this Court constantly

strives to determine and give effect to the intention of

the legislature.    Barr v. Town & Country Properties, Inc.,

240 Va. 292, 295, 396 S.E.2d 672, 674 (1990).

     The statute plainly states that the memorandum of

mechanic’s lien shall not include sums for materials

furnished more than 150 days prior to the last day that

material was furnished to the job preceding the filing of

the memorandum.    In the present case, Carolina Builders

filed its memorandum of mechanic’s lien on July 29, 1996.

The last day that Carolina Builders delivered materials to

the job immediately before it filed its memorandum was May

23, 1996.   Thus, under the clear terms of the statute, the

150 days must be counted back from May 23, 1996.   To adopt


                               5
Carolina Builder’s interpretation of the statute would, in

effect, rewrite the statute.

     A correct application of the statutory 150-day

limitation period does not render meaningless the 90-day

filing limitation, as hypothesized by Carolina Builders,

but instead comports with the General Assembly’s desire to

prevent undisclosed or inchoate liens.    Recognizing that

the 150-day limitation period might necessitate that a

claimant file multiple liens during the course of a

construction project, the General Assembly specifically

authorized the filing of “any number of memoranda.”    Code

§ 43-4.   The statute also allows a lien claimant to include

amounts that are “or will be due and payable.”    Code § 43-

4.

     The remaining issue is whether Carolina Builder’s

violation of the 150-day limitation rule renders its entire

mechanic’s lien unenforceable.     The circuit court so held,

but Carolina Builders argues that the 150-day requirement

limits only the sums that can be recovered and is not a

prerequisite for perfecting the mechanic’s lien.    Relying

on this Court’s decisions in West Alexandria Properties,

Inc. v. First Va. Mortgage & Real Estate Inv. Trust, 221

Va. 134, 267 S.E.2d 149 (1980); and First Nat’l Bank of

Martinsville v. Roy N. Ford Co., Inc., 219 Va. 942, 252


                               6
S.E.2d 354 (1979), Carolina Builders contends that, rather

than invalidating a lien, a trial court can reduce the

amount of a mechanic’s lien when the memorandum contains

excess sums.

     Conversely, Cenit argues that all the requirements in

Code § 43-4, including the 150-day limitation period, are

prerequisites for perfecting a mechanic’s lien and must,

therefore, be strictly construed.   According to Cenit,

Carolina Builders had an affirmative duty not to include

sums owed for materials furnished prior to the 150-day

“look back” period in its memorandum of mechanic’s lien.

Cenit also asserts that the decisions in West Alexandria

Properties and Bank of Martinsville are inapposite.    We

agree with Cenit.

     This Court has repeatedly stated that a mechanic’s

lien is in derogation of the common law and that the

statutes dealing with the existence and perfection of a

mechanic’s lien must, therefore, be strictly construed.

American Standard Homes Corp. v. Reinecke, 245 Va. 113,

119, 425 S.E.2d 515, 518 (1993); Rosser v. Cole, 237 Va.

572, 576, 379 S.E.2d 323, 325 (1989).   “[U]nless [a

mechanic’s lien] is perfected within the proper time and in

the proper manner, as outlined by the statute, it is lost.”

Wallace v. Brumback, 177 Va. 36, 40, 12 S.E.2d 801, 802


                             7
(1941).    In American Standard Homes, this Court

distinguished between perfection of a mechanic’s lien under

Code § 43-4 and enforcement of the lien pursuant to Code

§ 43-17.    In doing so, we stated that the “provisions of

the enforcement statutes are to be construed liberally

while the requirements of the perfection statute are to be

construed strictly.”   245 Va. at 119, 425 S.E.2d at 518.

     Code § 43-4 contains specific conditions that a lien

claimant must fulfill “in order to perfect the lien given

by § 43-3.”   For example, the claimant must file the

memorandum within a specified time (the 90-day rule) in the

clerk’s office where the property is located and must

include certain information in the memorandum.      The 150-day

limitation is included in these conditions.   In contrast to

the 90-day rule, the 150-day requirement is not a filing

deadline.    Instead, it is a limitation on how far back in

time a lien claimant can reach in any given memorandum for

sums owed.    Therefore, we conclude that the 150-day

limitation period is one of the prerequisites required by

Code § 43-4 in order to perfect a mechanic’s lien. 2    Thus,



     2
        Code § 43-15, which pertains to inaccuracies in the
memorandum or in the description of the property to be
covered by the lien, is not applicable to the present
situation.



                               8
the circuit court did not err when it held that Carolina

Builders’ mechanic’s lien was invalid and unenforceable.

     In reaching this result, we are mindful that we

allowed excess sums to be excluded without invalidating the

mechanic’s liens in West Alexandria Properties and Bank of

Martinsville.     In each of those cases, the memorandum of

mechanic’s lien included amounts attributable to labor

performed and materials furnished not only for improvements

on the liened land but also for improvements on additional

property.   However, the excess sums claimed in the

memoranda did not violate any specific statutory provision

in effect at that time with regard to perfecting a lien. 3

     In contrast, we invalidated the mechanic’s liens in

Woodington Elec., Inc. v. Lincoln Sav. & Loan Ass’n, 238

Va. 623, 385 S.E.2d 872 (1989), and in Rosser, 237 Va. 572,

379 S.E.2d 323.    In those cases, the lien claimants had

described property in the memoranda for which no labor or

materials had been furnished.       There was excess property

     3
        When this Court decided Kenbridge Constr., the 150-
day requirement was in effect, but it was not at issue in
that case. Although we acknowledged “that a trial court,
in certain limited circumstances, may reduce the amount of
a mechanic’s lien rather than invalidate the lien,” we did
not afford Kenbridge that relief. 248 Va. at 399, 448
S.E.2d at 662. Kenbridge had not requested that the trial
court reduce the lien so as to include only the value of
labor and materials furnished to the liened property, and



                                9
rather than excess sums included in the memoranda.   Noting

that Code § 43-4 requires the lien claimant to include in

the memorandum a brief description of the property on which

the lien is claimed, we stated in Woodington that “[i]t is

the mechanic’s duty to place his lien upon the property on

which he worked and no more.”    238 Va. at 634, 385 S.E.2d

at 878.   In other words, the lien claimant had violated one

of the specific provisions contained in Code § 43-4.

     Carolina Builders did not merely claim a larger sum

than its proof would perhaps support.   That kind of over-

inclusiveness is a traditional problem faced by a landowner

and one that a trial court resolves when determining how

much of a claimed lien should be allowed.    Id. at 633-34,

385 S.E.2d at 877-78.   Instead, Carolina Builders violated

the explicit statutory requirement that its memorandum

shall not include sums for materials furnished more than

150 days prior to the last day on which material was

furnished to the job preceding the filing of the

memorandum.   Code § 43-4.

     For these reasons, we will affirm the judgment of the

circuit court.

                                                     Affirmed.


_____________________
we doubted that it would have been able to make that
allocation. Id.

                                10