2021 VT 34
No. 2020-092
In re Champlain Parkway SW Discharge Permit Supreme Court
(Fortieth Burlington, LLC, Appellant)
On Appeal from
Superior Court,
Environmental Division
October Term, 2020
Thomas S. Durkin, J.
Judith L. Dillon of Lisman Leckerling, P.C., Burlington, for Appellant.
Thomas J. Donovan, Jr., Attorney General, and Robert F. McDougall, Assistant Attorney
General, Montpelier, for Appellee Vermont Agency of Natural Resources.
Jonathan T. Rose and Malachi T. Brennan of Dunkiel Saunders Elliott Raubvogel & Hand,
PLLC, Burlington, for Appellee City of Burlington.
PRESENT: Reiber, C.J., Robinson, Eaton, Carroll and Cohen, JJ.
¶ 1. COHEN, J. The City of Burlington and the Vermont Agency of Transportation
(VTrans) are jointly in the process of constructing the Champlain Parkway, a roadway project
intended to connect Interstate 189 to downtown Burlington and make numerous improvements to
the surrounding area. Fortieth Burlington, LLC (Fortieth) owns property adjacent to the project
and has challenged the decision of the Vermont Agency of Natural Resources (ANR) to grant the
project a renewed stormwater discharge permit. Fortieth argued before ANR and the
Environmental Division that the agency unlawfully waived a filing deadline in its 2017 stormwater
regulations and misinterpreted a provision of its 2017 Stormwater Management Manual. We
affirm the Environmental Division’s grant of summary judgment for the City and VTrans on these
claims.
I. Background
¶ 2. First, some background. In 10 V.S.A. § 1264, the Legislature directed ANR to
implement a stormwater permitting program and adopt rules to manage stormwater runoff
throughout the state. See id. § 1264(a)(2)(B), (f). On October 11, 2012, ANR granted the City a
stormwater discharge permit for the Champlain Parkway project. The permit expired five years
after the date of issue and provided: “The permittee shall reapply for a renewed discharge permit
ninety days prior to the expiration date of this permit.” The City’s permit was thus set to expire
on October 11, 2017.
¶ 3. Effective July 1, 2017, ANR promulgated a set of regulations to manage stormwater
discharge in the state. Environmental Protection Rules, Chapter 22, Stormwater Management Rule
for Stormwater-Impaired Waters [hereinafter 2017 Regulations], https://dec.vermont.gov/
sites/dec/files/documents/StormwaterManagementRule_ForStormwaterImpairedWaters_Ch22_F
inalAdopted_2016-12-15.pdf [https://perma.cc/3QJC-AWYF]. One of the 2017 regulations
provided: “A permittee who wishes to continue to discharge after the expiration date of . . . her
individual permit shall file an application for reissuance of the individual permit, on a form
provided by [ANR], at least 90 days prior to its expiration.” Id. § 22-309(k)(1).1
¶ 4. Also effective July 1, 2017, ANR adopted the 2017 Stormwater Management
Manual (VSMM). 2017 Vermont Stormwater Management Manual Rule and Design Guidance,
§ 1.4 [hereinafter 2017 VSMM], https://dec.vermont.gov/sites/dec/files/wsm/stormwater/docs/
Permitinformation/2017%20VSMM_Rule_and_Design_Guidance_04172017.pdf [https://perma
1
We refer to the ninety-day provisions in the permit and the 2017 regulations collectively
as “the filing deadline” or simply, “the deadline.” The agency has since adopted a new set of
regulations and rescinded the ninety-day provision. Environmental Protection Rules, Chapter 22,
Stormwater Permitting Rule, https://dec.vermont.gov/sites/dec/files/wsm/stormwater/docs/
2019_02_15%3B%20Final%20Adopted%20Chapter%2022%2C%20Stormwater%20Permitting
%20Rule.pdf [https://perma.cc/BYE4-29XR].
2
.cc/NGV5-LC6S]. The 2017 VSMM updates the stormwater management practices and site
design approaches of its predecessor, the 2002 VSMM. See id. § 1.0. As relevant here, the
transition clause of the 2017 VSMM provides that “the standards in the 2002 VSMM shall apply
to a project if the redevelopment or expansion is a public transportation project, and as of January
1, 2017, the Agency of Transportation or the municipality principally responsible for the project
has initiated right-of-way valuation activities.” Id. § 1.4.
¶ 5. It is uncontested that the City filed an application to renew the permit on September
15, 2017—after the filing deadline, but twenty-six days before the permit was set to expire. ANR
accepted the City’s filing as timely and placed a proposed, renewed permit up for public comment,
essentially waiving the deadline.
¶ 6. Fortieth filed comments challenging the proposed permit, among other reasons,
because the City did not comply with the filing deadline and because the renewal application did
not indicate compliance with the 2017 VSMM. ANR rejected the deadline challenge, concluding
that the application was timely because it was filed before the permit expired. The agency also
rejected the VSMM challenge, pointing to the 2017 VSMM transition clause. It thus issued the
project a renewed permit and indicated that the project complied with the 2017 regulations and the
2002 VSMM.
¶ 7. Fortieth appealed to the Environmental Division, arguing that the filing deadline
had to be enforced as written and that the project did not qualify for the transition clause of the
2017 VSMM because right-of-way valuation activities were not initiated until after January 1,
2017. The City and ANR moved for partial summary judgment on the deadline issue. They argued
that the filing deadline was waivable as a mere procedural rule designed to benefit ANR and that
the waiver did not prejudice Fortieth in any respect. The movants submitted evidence that it was
ANR’s consistent practice to accept renewal applications filed after the filing deadline if they were
submitted before the permit expired. The Environmental Division agreed that the deadline was an
3
internal procedural rule, deviation from which resulted in no prejudice. The court therefore granted
partial summary judgment on this issue.
¶ 8. Separately, the City moved for partial summary judgment on the VSMM issue and
marshalled evidence that right-of-way valuation activities were initiated as far back as the 1980s,
when the first steps were taken to secure a right-of-way for the project, and more recently in 2016,
when property valuation activities were undertaken for a new section of the roadway. The
Environmental Division granted partial summary judgment for the City on this issue as well.
¶ 9. We review the Environmental Division’s grant of summary judgment without
deference, and we apply the same standard as that court. In re Mathez Act 250 LU Permit, 2018
VT 55, ¶ 5, 207 Vt. 537, 192 A.3d 400. Summary judgment is appropriate “when there is no
genuine issue of material fact and the moving party is entitled to judgment as a matter of law.” Id.
II. ANR’s Waiver of the Filing Deadline
¶ 10. On appeal, Fortieth first argues that the plain language of the permit and the 2017
regulations must be enforced without deferring to the agency’s interpretation. It argues that the
permit and regulations do not confer discretion on ANR to waive the filing deadline it adopted.
Fortieth further contends that the deadline is not an internal procedural rule that ANR can disregard
and that it was prejudiced by the agency’s waiver of the deadline.
¶ 11. As a preliminary matter, there is no agency interpretation to defer to in this deadline
issue. While we defer to an agency’s interpretation of its own regulations, see, e.g., In re Joyce,
2018 VT 90, ¶ 18, 208 Vt. 226, 197 A.3d 378, ANR did not interpret the 2017 regulations or the
permit differently than their plain meanings dictate. The regulations and the permit are
unambiguous: A permittee must file for renewal ninety days prior to the expiration date of the
permit. See supra, ¶¶ 2-3. ANR did not interpret these provisions otherwise; it waived the deadline
altogether. Moreover, this is not a case where a substantive issue requiring agency interpretation
is woven into a procedural matter, as in In re Stowe Cady Hill Solar, LLC, where an agency rule
required the agency to determine whether certain applications “substantially” complied with
4
prescribed requirements. 2018 VT 3, ¶ 19, 206 Vt. 430, 182 A.3d 53. ANR’s action here of
waiving a filing deadline in its own regulations is the type of procedural ruling we review for abuse
of discretion, which exists “where an agency has declined to exercise its discretion or has done so
on untenable or unreasonable grounds.” Id. ¶ 17.
¶ 12. We accordingly consider whether ANR abused its discretion in waiving the filing
deadline it established. Generally, administrative agencies must follow their own regulations until
they rescind or amend them. This settled principle is reflected in our state law, federal law, and
the law of other states. See, e.g., Columbia Broad. Sys., Inc. v. United States, 316 U.S. 407, 422
(1942); Jordan Towing, Inc. v. Hebbville Auto Repair, Inc., 800 A.2d 768, 777 (Md. 2002); N.Y.
Times Co. v. Comm’r of Revenue, 693 N.E.2d 682, 685 (Mass. 1998); In re Peel Gallery of Fine
Arts, 149 Vt. 348, 351, 543 A.2d 695, 697 (1988). But, as ever, there are exceptions to the rule.
¶ 13. The U.S. Supreme Court adopted one such exception in American Farm Lines v.
Black Ball Freight Services, 397 U.S. 532 (1970). There, federal statutes granted the Interstate
Commerce Commission (ICC) the power to grant motor carriers expedited, temporary operating
authority to meet urgent transportation needs. Further to that power, the ICC promulgated rules
requiring applications for temporary authority to include statements with specified information
designed to establish the need for the temporary authority. American Farm Lines filed an
application with statements generally describing the need for the authority but omitting some of
the specified information required by the ICC rule. The ICC nevertheless granted the application,
an action other carriers challenged as an unlawful failure of the ICC to require strict compliance
with its own rules.
¶ 14. The Court observed that the agency was “entitled to a measure of discretion in
administering its own procedural rules.” Id. at 538. It then held that an agency may waive a
procedural rule “adopted for the orderly transaction of business” to aid the agency in exercising its
discretion and “not intended primarily to confer important procedural benefits upon individuals in
the face of otherwise unfettered discretion.” Id. at 538-39. Such a waiver may be lawful if the
5
agency does not fail to exercise discretion mandated by rule, and no “substantial prejudice” befalls
a complaining party. Id. at 539. The Court there considered that the failure to supply the required
information did not prejudice the protesting carriers in voicing their objections to the application.
Id.
¶ 15. The federal courts of appeal have since applied American Farm Lines to uphold
agency waivers of administrative deadlines such as the one at issue here. For example, the Court
of Appeals for the D.C. Circuit upheld the ICC’s acceptance of a late petition for a stay of an order
where the deadline was “designed not primarily to safeguard private rights but rather to facilitate
the Commission’s orderly transaction of its business” and there was no substantial prejudice to
complaining parties. Dana Corp. v. ICC, 703 F.2d 1297, 1300 (D.C. Cir. 1983); see also Health
Sys. Agency of Okla., Inc. v. Norman, 589 F.2d 486, 489-90 (10th Cir. 1978) (holding that agency
had discretion to waive filing deadline administratively chosen to ensure that applications were
received with time to review and make necessary determination).
¶ 16. State high courts have embraced the American Farm Lines exception as their own.
See, e.g., Forquer v. State, Commercial Fisheries Entry Comm’n, 677 P.2d 1236, 1243-44 (Alaska
1984); Pollock v. Patuxent Inst. Bd. of Review, 823 A.2d 626, 650 (Md. 2003); W. Bloomfield
Hosp. v. Certificate of Need Bd., 550 N.W.2d 223, 227 (Mich. 1996). We join these courts in
adopting American Farm Lines as a sound principle of state administrative law. Failure to do so
would force agencies to adhere inflexibly to all their procedural rules, producing irrational
consequences in many cases and resulting injustice. Or, it would deter agencies from adopting
numerous procedural rules that facilitate their work, creating unnecessary administrative
inefficiency.
¶ 17. But the exception is strictly circumscribed by American Farm Lines itself and our
established principles governing agency application of regulations. To invoke the exception, the
agency action must first and foremost be consistent with governing statutes. See, e.g., Stowe Cady
Hill Solar, 2018 VT 3, ¶ 21 (observing that agency regulations cannot be “applied in a way that
6
exceeds the statutory mandate under which the regulation was promulgated”); Martin v. State,
Agency of Transp. Dep’t of Motor Vehicles, 2003 VT 14, ¶ 28, 175 Vt. 80, 819 A.2d 742
(“Agencies generally may not choose to ignore their statutory mandate because they believe it is
administratively inefficient or infeasible.” (quotation omitted)). Second, the rule at issue must be
a procedural rule adopted for the orderly transaction of business to aid the agency in exercising its
discretion, not one intended to confer important procedural benefits upon individuals. Am. Farm
Lines, 397 U.S. at 538-39. Third, the agency action must not substantially prejudice a complaining
party. Id. at 539. Fourth, the agency action cannot constitute a failure to exercise independent
discretion mandated by regulation. Id.; see also Bennington Hous. Auth. v. Bush, 2007 VT 60,
¶¶ 13-14, 182 Vt. 133, 933 A.2d 207 (holding that agency abused its discretion in evicting entire
family following lease violation of one member when regulations granted agency more flexible
discretion in addressing such violations). Finally, the agency must apply the rule consistently, not
arbitrarily, unreasonably, or discriminatorily. Stowe Cady Hill Solar, 2018 VT 3, ¶ 21 (“A
fundamental norm of administrative procedure requires an agency to treat like cases alike.”
(quotation omitted)); see also In re Apple Hill Solar LLC, 2019 VT 64, ¶ 25, 211 Vt. 54, 219 A.3d
1295 (noting that agency departure from prior holdings “cannot rest on bases that are arbitrary,
unreasonable, or discriminatory”).
¶ 18. ANR complied with the above requirements in waiving the filing deadline and
consequently did not abuse its discretion. To begin, the agency action is consistent with the
governing statute. Among other things, the stormwater management statute directs ANR to
implement a stormwater permitting program, grants the agency the power to adopt rules to manage
the program, outlines land uses requiring a discharge permit, and specifies that a permit is valid
for a period “not to exceed five years.” See 10 V.S.A. § 1264(a)(2)(B), (c), (f), (h)(1). Although
the statute establishes certain substantive requirements for permit renewal, see, e.g., id.
§ 1264(h)(2)(A)(ii), it does not specify the process for renewal or mandate the ninety-day filing
deadline.
7
¶ 19. For interrelated reasons, the filing deadline was a procedural rule adopted for the
orderly transaction of business to aid the agency in exercising its discretion; it was not intended to
confer important procedural benefits upon individuals; and the waiver did not result in prejudice.
The rule did not regulate the agency’s determination of whether the project complied with
substantive requirements to renew a permit. It did not even govern the information required in
renewal applications. The permittee and the public would have been in the same position if the
renewal application had been filed ninety-one days before expiration as they were when it was
filed twenty-six days before expiration. ANR’s substantive review of the permit was no different
in the second instance than in the first.
¶ 20. Nor was the deadline adopted to allow other parties sufficient time to oppose or
otherwise influence the renewal. Like the protesting carriers in American Farm Lines, Fortieth
had an unhindered opportunity to voice its concerns or opposition to the renewal. See 397 U.S. at
538. ANR’s regulations required the agency to determine when a renewal application was
complete and then submit the application and a draft, renewed permit to at least thirty days of
public comment or an extended public-comment period. See 2017 Regulations, supra, § 22-
309(k)(1) (“A renewal application shall be noticed subject to the public participation requirements
set forth in subsection 309(d) of this section.”); id. § 22-309(d) (establishing thirty-day comment
period with possibility of extension and public hearing). Once ANR accomplished these tasks, the
public had at least thirty days to comment, regardless of when the application was filed. Fortieth
fully availed itself of that process.
¶ 21. Fortieth argues that the waiver resulted in prejudice because the City was allowed
to renew the permit under an older set of stormwater regulations than those in effect at the time of
renewal. It maintains that if the City had been forced to apply for an entirely new permit, the new
regulations would have applied. We disagree. First, though ANR reviewed the permit under the
2002 VSMM, it did apply the 2017 regulations. Thus, the project was not allowed to circumvent
all existing regulations at the time of renewal. Second, the fact that the permit was subjected to
8
the 2002 VSMM instead of the 2017 VSMM is a function of ANR’s regulatory choice to adopt
the transition clause and its determination that the project satisfied the clause. The 2002 VSMM
would have applied whether ANR processed the City’s application as a renewal or as a new
application, and thus irrespective of ANR’s waiver of the deadline to renew. No prejudice
stemmed from renewal or the deadline waiver.
¶ 22. Finally, because the agency action here did not constitute a failure to exercise
independent discretion mandated by regulation, what remains is to determine whether the agency
applied the rule inconsistently. Before the Environmental Division, the City and ANR submitted
an affidavit from the program manager of ANR’s stormwater program, who had applied the
agency’s stormwater regulations and issued permits since 2007. According to the manager, ANR
processed permit renewal applications received beyond the filing deadline, considered a renewal
application to be timely if it was filed before the permit expired, and in his experience, ANR had
never denied a renewal application for failure to comply with the filing deadline. A former ANR
stormwater district manager from 2010 to 2016 echoed these statements in a separate affidavit.
Fortieth disputed these statements but did not adduce any evidence to contradict them. Although
we consider the summary judgment record in the light most favorable to the nonmoving party, that
party may not “rest on bare allegations to demonstrate that disputed material facts remain.” Baptie
v. Bruno, 2013 VT 117, ¶ 10, 195 Vt. 308, 88 A.3d 1212 (quotation omitted). Given the
unchallenged record evidence that the agency has applied the rule consistently, we consider the
fact undisputed. See V.R.C.P. 56(c)(1)(A), (e)(2). There is no genuine dispute as to any material
fact, and the City and ANR are entitled to judgment as a matter of law on the deadline issue.
¶ 23. We do not easily deviate from the principle that “[a]n administrative agency must
abide by its regulations as written until it rescinds or amends them.” Peel Gallery, 149 Vt. at 351,
543 A.2d at 697. This was and remains the law. But, when an agency scrupulously satisfies the
elements we have here outlined, fairness demands the exception as much as the rule.
9
III. Transition Clause of the 2017 VSMM
¶ 24. The second issue on appeal is whether ANR erred in concluding that the project
qualifies for the transition clause of the 2017 VSMM, which allows the project to implement the
standards of the 2002 VSMM. Fortieth contends that the project does not qualify because right-
of-way valuation activities were not initiated until after January 1, 2017. Specifically, it argues
that these activities were not begun by that date because certain right-of-way plans mandated by
the 2012 Vermont Agency of Transportation’s Right-of-Way Manual (VTrans Manual) were not
completed until April 2018 and a necessity hearing required under 19 V.S.A. § 502 did not occur
until May 2018.
¶ 25. In determining that the project satisfied the transition clause, ANR interpreted its
own rules, employing its expertise in a regulatory area statutorily entrusted to it. See 10 V.S.A.
§ 1264. We therefore accord substantial deference to the agency’s interpretation of the VSMM.
In re ANR Permits in Lowell Mountain Wind Project, 2014 VT 50, ¶¶ 15, 17, 196 Vt. 467, 98
A.3d 16 (extending substantial deference to ANR interpretation of VSMM because
“[i]nterpretation of the VSMM is squarely within ANR’s expertise as its authoring agency”). We
nevertheless undertake an independent review and “will overturn an agency’s interpretation of its
own promulgated regulation that exceeds the authority granted under the state enabling statute;
that conflicts with past agency interpretations of the same rule; that results in unjust, unreasonable
or absurd consequences; or that demonstrates compelling indications of error.” In re Conservation
Law Found., 2018 VT 42, ¶ 16, 207 Vt. 309, 188 A.3d 667 (quotations omitted) (citations omitted).
There is no such showing here.
¶ 26. This Court construes administrative rules “to discern the intent of the drafters, and
we so do by examining the plain meaning of the regulatory language.” Id. ¶ 15; see also In re
Vitale, 151 Vt. 580, 584, 563 A.2d 613, 616 (1989) (“The primary rule when reviewing
construction of an administrative rule is to give language its plain, ordinary meaning.”). Under
the relevant portion of the transition clause, the standards in the 2002 VSMM apply to this
10
concededly public transportation project if “as of January 1, 2017, the Agency of Transportation
or the municipality principally responsible for the project has initiated right-of-way valuation
activities.” 2017 VSMM, supra, § 1.4 (emphasis added). To “initiate” means “to cause or facilitate
the beginning of” something. Initiate, Merriam Webster Online Dictionary, https://www.merriam-
webster.com/dictionary/initiate [https://perma.cc/4G63-CZKY]. “Valuation” means “[t]he
process of determining the value of a thing or entity,” Valuation, Black’s Law Dictionary (11th
ed. 2019), or more specifically, “appraisal of property,” Valuation, Merriam Webster Online
Dictionary, https://www.merriam-webster.com/dictionary/valuation [https://perma.cc/9R7X-
J8EJ]. Plainly, the drafters intended the transition clause to apply to projects for which the process
of appraising the land necessary to build the project had begun as of January 1, 2017.
¶ 27. The plain language of the transition clause is inconsistent with Fortieth’s suggestion
that the clause is tied to the timing of the necessity hearing required under 19 V.S.A. § 502(c) to
acquire property to construct a highway. The clause does not reference this statute or provide other
evidence of the reference Fortieth suggests. Nor does the language of the transition clause support
Fortieth’s argument that the clause references the 2012 VTrans Manual. If the drafters of the
transition clause had intended to make the clause turn on 19 V.S.A. § 502 or the VTrans Manual,
they would have referenced the statute or the manual.2
¶ 28. Finally, there is evidence in this record that right-of-way valuation activities had
been initiated as of January 1, 2017. Before the Environmental Division, the City filed two
affidavits indicating that right-of-way valuation activities were undertaken in the 1980s and in
2
We do not interpret the statute or the manual here. But we do note that the statute and
the part of the manual Fortieth identifies refer to acquisition of property, not property valuation
activities. See 19 V.S.A. § 502(c)(1) (“A public hearing shall be held . . . prior to the Agency’s
initiating proceedings under this chapter for the acquisition of any property.”); Vermont Agency
of Transportation 2012 Right of Way Manual, 2-5, https://vtrans.vermont.gov/sites/aot/
files/highway/documents/rightofway/RightofWayManual2012.pdf [https://perma.cc/YDB29LZJ]
(“Right of way plans are prepared . . . to provide the title and technical data necessary when
acquiring land and/or rights for the construction of transportation projects.”). We see nothing in
the statute or cited portion of the manual prohibiting or discouraging the initiation of property
valuation activities until the public hearing or right-of-way plans are finalized.
11
2016. The City’s assistant director of public works, responsible for overseeing development of
the project, attested that valuation to build a southern portion of the roadway began in the 1980s.
The director also stated that in 2016, VTrans undertook valuation activities for a northern portion
of the project. VTrans’ acquisition chief, who has worked on the project since the 1980s, provided
the same information. Fortieth did not produce any evidence contesting these statements and
therefore failed to create a genuine dispute of fact. See Baptie, 2013 VT 117, ¶ 10; V.R.C.P.
56(c)(1)(A), (e)(2). The agency’s interpretation of the transition clause is consistent with its plain
language and was reasonably applied to the facts before us. We find no inconsistency with the
governing statute or previous agency interpretations, no unjust, unreasonable, or absurd
consequences, and no compelling indications of error. The City is entitled to judgment as a matter
of law on this issue.
Affirmed.